Swarm Satellites Launched Successfully

Eurockot Launch Services GmbH successfully launched the three satellite Swarm constellation for the European Space Agency today at 12:02 hrs […]

Posted in News, Swarm Mission | Comments Off on Swarm Satellites Launched Successfully

Daily 64 (L-1)

Today the Military Space Forces have started to fuel the first 2 stages of the Rocket with fuel and oxidizer. […]

Posted in Swarm Mission | Comments Off on Daily 64 (L-1)

Daily 63 (L-2)

While the last works are done to prepare the rocket booster fuelling which takes place tomorrow morning, the customer and […]

Posted in Swarm Mission | Comments Off on Daily 63 (L-2)

Daily 62 (L-3)

Today was the day of the „Dress Rehearsal“. The launch day was copied and all spacecraft operations were performed as […]

Posted in Swarm Mission | Comments Off on Daily 62 (L-3)

Daily 61 (L-4)

Today the train transporting the Upper Composite (Space Head) has left the MIK at about 6h in the morning and […]

Posted in Swarm Mission | Comments Off on Daily 61 (L-4)

Daily 60 (L-5)

While the Astrium team starts packing the first equipment, the upper composite (space head) was moved to the general hall, […]

Posted in Swarm Mission | Comments Off on Daily 60 (L-5)

Daily 59 (L-6)

Today the encapsulation of the Swarm satellites has taken place. The both fairing halves were moved from their storage position […]

Posted in Swarm Mission | Comments Off on Daily 59 (L-6)

Daily 58 (L-7 corrected)

Today the switch on and the electrical checks of the 3 Swarm satellites after mating with the Breeze upper stage […]

Posted in Swarm Mission | Comments Off on Daily 58 (L-7 corrected)

Daily 57

Today the Breeze-KM upper stage arrived fuelled in the integration facility MIK. After lunch the adapter system with the three […]

Posted in Swarm Mission | Comments Off on Daily 57

Daily 56 (L-11)

Today the launcher upper stage was fuelled with the oxidizer. After successful fuelling, the Breeze-KM upper stage will be moved […]

Posted in Swarm Mission | Comments Off on Daily 56 (L-11)

Daily 55 (L-12)

While the Upper Stage was filled with compressed gases  today, the payload fairing was prepared in 101B. Several meetings and […]

Posted in Swarm Mission | Comments Off on Daily 55 (L-12)

Daily 54 (L-13)

Today all parties used the time for several preparation meetings for example for back transportation and movement of the electrical […]

Posted in Swarm Mission | Comments Off on Daily 54 (L-13)

Daily 53 (Day Off)

While the Breeze-KM upper stage has been fuelled this weekend, the Swarm spacecraft team went to Archangelsk to enjoy local […]

Posted in Swarm Mission | Comments Off on Daily 53 (Day Off)

Daily 52 (L-14)

Today the lifting device for the adapter system was installed in the cleanroom 101A so that in the evening the […]

Posted in Swarm Mission | Comments Off on Daily 52 (L-14)

Daily 51 (L-15)

On this Thursday morning in the cleanroom 101A, some remaining parts of Multi Layer Insulation (MLI) were installed on the […]

Posted in Swarm Mission | Comments Off on Daily 51 (L-15)

Swarm Launch from Plesetsk on 22 November 2013

The new launch date for the ESA’s Magnetic Field Mission, originally scheduled for 14 November, is confirmed for 22 November […]

Posted in News, Swarm Mission | Comments Off on Swarm Launch from Plesetsk on 22 November 2013

Daily 50

Today the ESA and Astrium teams switched on the SWARM satellite FM3 and successfully checked the electrical components of the […]

Posted in Swarm Mission | Comments Off on Daily 50

Daily 49

Today the 3rd and last SWARM satellite (FM 3) was successfully mounted on the launch vehicle adapter system. In cleanroom […]

Posted in Swarm Mission | Comments Off on Daily 49

Daily 48

The SWARM spacecraft flight model 2 was successfully electrically checked in 101A. At the same time the Breeze-KM upper stage […]

Posted in Swarm Mission | Comments Off on Daily 48

Daily 47

While the ESA, Astrium and Eurockot teams had a day off, the upper stage Breeze-KM together with the first two […]

Posted in Swarm Mission | Comments Off on Daily 47

Daily 46

On this Saturday the second Swarm spacecraft was successfully hoisted on the launch vehicle adapter system. The upper stage was […]

Posted in Swarm Mission | Comments Off on Daily 46

Daily 45

In the cleanroom 101A Khrunichev has prepared the interface brackets which shall be mated with the Swarm Flight Model (FM) […]

Posted in Swarm Mission | Comments Off on Daily 45

Daily 44

The day started with the mounting of the interface brackets on the first SWARM satellite (FM1). After a visual inspection […]

Posted in Swarm Mission | Comments Off on Daily 44

Daily 43

Today the day has started with the formal readiness review for mating of the first satellite on the launcher adapter […]

Posted in Swarm Mission | Comments Off on Daily 43

Daily 42

The launch preparation activities continue. The picture shows the three spacecraft in vertical position ready for installation onto the adapter […]

Posted in Swarm Mission | Comments Off on Daily 42

Daily 41 (L-16)

Today the three spacecraft were moved into vertical position. This was done in preparation of their installation onto the adapter […]

Posted in Swarm Mission | Comments Off on Daily 41 (L-16)

Daily 40 (Day Off)

Today was a day off. Some members of the team took the chance to make a trip to the town […]

Posted in Swarm Mission | Comments Off on Daily 40 (Day Off)

Daily 39 (L-17)

While the joint operations of the spacecraft team and the launch vehicle team is coming closer, the satellites are powered […]

Posted in Swarm Mission | Comments Off on Daily 39 (L-17)

Daily 38 (L-18)

While further electrical checks are conducted at the launch pad, the joint operations expected to start next week are further […]

Posted in Swarm Mission | Comments Off on Daily 38 (L-18)

Daily 37 (L-19)

The Swarm launch campaign now approaches the phase of joint operations during which the three Swarm satellites are integrated on […]

Posted in Swarm Mission | Comments Off on Daily 37 (L-19)

Daily 36 (L-20)

After the successful installation of the Rockot booster unit to the launch pad the operations continue in the integration facility […]

Posted in Swarm Mission | Comments Off on Daily 36 (L-20)

Daily 35 (L-21)

Today very important milestones for the Rockot launch vehicle preparation have been accomplished. This includes the transfer of the booster […]

Posted in Swarm Mission | Comments Off on Daily 35 (L-21)

Daily 34 (L-22)

At Eurockot’s launch site in the Plesetsk Cosmodrome the Swarm launch campaign today continues with the dry-run of the launch […]

Posted in Swarm Mission | Comments Off on Daily 34 (L-22)

Daily 33 (L-23)

During this weekend electrical checkouts of the launch vehicle are conducted to prepare the launch of the three Swarm satellites. […]

Posted in Swarm Mission | Comments Off on Daily 33 (L-23)

Daily 32 (L-24)

The Swarm launch campaign continues at Eurockot’s launch site in Northern Russia with preparations to transport the booster unit to […]

Posted in Swarm Mission | Comments Off on Daily 32 (L-24)

Daily 31 (L-25)

At the Rockot integration facility MIK the dispenser system is unpacked and assembled after having been transported to the cosmodrome […]

Posted in Swarm Mission | Comments Off on Daily 31 (L-25)

Daily 30 (L-26)

Today the launch vehicle preparations for ESA Swarm mission continue with the transfer of the Transport & Launch Container Extension […]

Posted in Swarm Mission | Comments Off on Daily 30 (L-26)

Daily 29 (L-27)

Snow has arrived at the Plesetsk Cosmodrome where preparation to launch ESA’s Swarm continues with the pneumatic checks of the […]

Posted in Swarm Mission | Comments Off on Daily 29 (L-27)

Daily 28 (L-28)

The work on the launch vehicle (LV) and spacecraft (SC) has been continued today. All activities with the LV transportation […]

Posted in Swarm Mission | Comments Off on Daily 28 (L-28)

Daily 27 (Day Off)

Today is a day off for the Swarm launch team. Therefore, we decided to spend it in the best way […]

Posted in Swarm Mission | Comments Off on Daily 27 (Day Off)

Daily 26 (L-29)

While all three Swarm spacecraft have been reunited in clean room 101A, the Breeze-KM upper stage, unloaded into the General […]

Posted in Swarm Mission | Comments Off on Daily 26 (L-29)

Daily 25 (L-30)

The propellant loading for Swarm spacecraft FM1 has been completed so that it is ready to be moved back from […]

Posted in Swarm Mission | Comments Off on Daily 25 (L-30)

Daily 24 (L-31)

The Freon loading on the third Swarm spacecraft (FM1) continued while the other two spacecraft (FM2, FM3) underwent further functional […]

Posted in Swarm Mission | Comments Off on Daily 24 (L-31)

Daily 23 (L-32)

Today the Freon loading of the third spacecraft (Flight Model 1) has started. In parallel to this activity the work […]

Posted in Swarm Mission | Comments Off on Daily 23 (L-32)

Daily 22 (L-33)

Tuesday, October 8, 2013, started with further Swarm No. 1 satellite processing for the Freon loading. The loading itself is […]

Posted in Swarm Mission | Comments Off on Daily 22 (L-33)

Daily 21 (L-34)

The fuelling team has rearranged the Freon loading equipment today. The Swarm No.1 was moved to 101B so that Astrium […]

Posted in Swarm Mission | Comments Off on Daily 21 (L-34)

Daily 20 (Day Off)

This Sunday is the second day off since start of the launch campaign. The entire team enjoys the nice weather […]

Posted in Swarm Mission | Comments Off on Daily 20 (Day Off)

Daily 19 (L-35)

Today the Astrium fuelling team has completed the Freon loading of the Swarm  No. 2 in cleanroom 101B. The Swarm […]

Posted in Swarm Mission | Comments Off on Daily 19 (L-35)

Daily 18 (L-36)

Spacecraft loading with Freon has continued today with Swarm No. 2 while the other two spacecraft were undergoing electrical checkouts. […]

Posted in Swarm Mission | Comments Off on Daily 18 (L-36)

Daily 17 (L-37)

Today the Astrium fuelling team has started the Freon loading of the Swarm No. 2 in cleanroom 101B. The Swarm […]

Posted in Swarm Mission | Comments Off on Daily 17 (L-37)

Daily 16 (L-38)

Yesterday evening the three Swarm satellites were rearranged in the cleanrooms. The freon loaded Swarm No.1 was moved in 101A […]

Posted in Swarm Mission | Comments Off on Daily 16 (L-38)

Daily 15 (L-39)

Fuelling continued in Hall 101B. The spacecraft undergo thorough checkout of its systems before and after fuelling. For this purpose the […]

Posted in Swarm Mission | Comments Off on Daily 15 (L-39)

Daily 14 (L-40)

Today, the three Swarm spacecraft underwent different treatments. The battery of spacecraft No. 1 was charged. A functional test was […]

Posted in Swarm Mission | Comments Off on Daily 14 (L-40)

Daily 13 (Day Off)

Today, Sunday is the first Sunday off since the beginning of the Launch Campaign. The weather was cold, about 0°C […]

Posted in Swarm Mission | Comments Off on Daily 13 (Day Off)

Daily 12 (L-41)

Today the Freon loading of the Swarm satellite No. 3 was continued. For safety reasons only a minimum number of […]

Posted in Swarm Mission | Comments Off on Daily 12 (L-41)

Daily 11 (L-42)

The day at MIK started with Freon loading of the Swarm No. 3 (see Fig.1). In parallel to this activity, […]

Posted in Swarm Mission | Comments Off on Daily 11 (L-42)

Daily 10 (L-43)

While the SWARM spacecraft flight model 2 was prepared for hoisting in 101A (see figure 1), the SWARM spacecraft flight […]

Posted in Swarm Mission | Comments Off on Daily 10 (L-43)

D 9 (L-44)

Today, on September 25, the weather has broken in Plesetsk: the winter has arrived.         In MIK the […]

Posted in Swarm Mission | Comments Off on D 9 (L-44)

Daily 8 (L-45)

The working day in Plesetsk started with the installation and preparation of the fuelling equipment.  The fuelling of the first […]

Posted in Swarm Mission | Comments Off on Daily 8 (L-45)

Daily 7 (L-46)

After the arrival of the SC fueling team from Astrium UK yesterday, the unloading of the container with the fuelling […]

Posted in Swarm Mission | Comments Off on Daily 7 (L-46)

Daily 6 (L-47)

Though today is Sunday, nevertheless the launch campaign activities were going on. Today the container with the last satellite, the […]

Posted in Swarm Mission | Comments Off on Daily 6 (L-47)

Daily 5 (L-48)

Today the work at MIK has been continued. The Astrium experts performed installation of electrical and mechanical ground support equipment. Meanwhile, […]

Posted in Swarm Mission | Comments Off on Daily 5 (L-48)

Daily 4 (L-49)

The second of three Swarm satellites with its ground support equipment has arrived in good shape at the Rockot integration […]

Posted in Swarm Mission | Comments Off on Daily 4 (L-49)

Daily 3 (L-50)

Today Swarm No.2 and its GSE arrived in Plesetsk Cosmodrome by IL-76 cargo plane from Munich. After landing the containers […]

Posted in Swarm Mission | Comments Off on Daily 3 (L-50)

Daily 2 (L-51)

After the first Swarm spacecraft container and two GSE containers were offloaded from the trucks in the MIK yesterday, the […]

Posted in Swarm Mission | Comments Off on Daily 2 (L-51)

Daily 1 (L-52)

The first of the three Swarm spacecraft took off this morning from Munich airport. The IL-76 cargo plane first flew […]

Posted in Swarm Mission | Comments Off on Daily 1 (L-52)