Swarm Mission

Daily 26 (L-29)

While all three Swarm spacecraft have been reunited in clean room 101A, the Breeze-KM upper stage, unloaded into the General […]

Daily 25 (L-30)

The propellant loading for Swarm spacecraft FM1 has been completed so that it is ready to be moved back from […]

Daily 24 (L-31)

The Freon loading on the third Swarm spacecraft (FM1) continued while the other two spacecraft (FM2, FM3) underwent further functional […]

Daily 23 (L-32)

Today the Freon loading of the third spacecraft (Flight Model 1) has started. In parallel to this activity the work […]

Daily 22 (L-33)

Tuesday, October 8, 2013, started with further Swarm No. 1 satellite processing for the Freon loading. The loading itself is […]