Swarm Mission

Daily 41 (L-16)

Today the three spacecraft were moved into vertical position. This was done in preparation of their installation onto the adapter […]

Daily 40 (Day Off)

Today was a day off. Some members of the team took the chance to make a trip to the town […]

Daily 39 (L-17)

While the joint operations of the spacecraft team and the launch vehicle team is coming closer, the satellites are powered […]

Daily 38 (L-18)

While further electrical checks are conducted at the launch pad, the joint operations expected to start next week are further […]

Daily 37 (L-19)

The Swarm launch campaign now approaches the phase of joint operations during which the three Swarm satellites are integrated on […]