Daily 52 (L-14)

Today the lifting device for the adapter system was installed in the cleanroom 101A so that in the evening the adapter with the 3 SWARM satellites could be lifted on the dolly.

On the launcher side the Breeze-KM upper stage was transferred back to the integration facility MIK. In the cleanroom 101B Khrunichev specialists have started demating the fairing halves from the so called Spacehead.